Forbes to West Jemalong Transmission Line

Langford and Rowe were contracted to conduct a 30-metre wide, 40km long detail profile on behalf of Essential Energy for a replacement transmission line between two of its large substations. The profile survey was completed using GPS and a Laser Scanning to cover vast distances in the shortest timefram possible. By utilising these technologies, L&R were able to complete the field work in 20 days (which is an average of 2km/day for a full detail survey!)